In WaterGems whenever I give a loop pipe network to Darwin designer in order to optimize the pipe diameter, it never gives results in decreasing order of the pipe dia, rather it is quite random. Can I know the reasons?? What could be the correct method?
For Example:
In the above pipe network (which I have made just for practice), when I use Darwin Designer for all the pipes the dia is in between 200-300mm but for red one it is 2500, if I manually decrease the dia of red marked pipe to 300 then even at that dia all other pressure criterias are fulfilled along with that of velocity.
Check out the "tips" help topic that Terry mentioned, item # 7:
Designer keeps coming up with pipe sizes that change up or down in size. I wouldn't construct such a design; what can I do?
Darwin Designer applies a competent genetic algorithm to optimize the design. It does not require or have any domain-specific knowledge about the water system, which ensures it is a generic tool, but also causes some side-effect for some design cases-like giving up-or-down pipe sizes. In particular, the solutions are evaluated by comparing the fitness values of solutions. Darwin Designer will assume a pipeline with pipe sizes that go up and down (to meet required pressures as closely as possible) is better than one that has a constant size that exceeds the pressures at some locations, since there is no specific penalty assigned to the fitness of a solution that has pipes that change up and down in size. It is, therefore, up to you to control the eventual design and this can be done by different means, as follows:
To better illustrate this concept, consider a run of four pipes in series, each with different lengths. For these four pipes, the controlling pressure is the downstream-most junction, and all intermediate junctions are well above the required pressure. Now, after Darwin Designer finishes designing the run of pipe, it selects the first pipe as a 16 in., the second as 12 in., the third as 16 in. and the fourth as 12 in. It is unlikely that this design would be constructed as-is, but if the pipes themselves represented sufficient length of pipe, then it may be practical to construct a portion of the pipeline as 16 in. and a portion as 12 in. If this is the case, then you need to look at the model to determine why Darwin Designer is changing the third pipe back up to 16 in. It may be that since the downstream-most junction is the only controlling node, that Darwin Designer is merely trying to achieve the right head-loss in the total pipe length, by choosing the length of pipe that should be 16 in. and the length that should be 12 in. Of course, it is still constrained by the individual pipe lengths in the model, but if they are different, the optimization algorithm will use this fact to its advantage. In this case, it may very well be that Designer is saying construct a total of 1500 ft. of 16-in. and 1000 ft. of 12-in. pipe, and not necessarily 850 feet of 16-in., 600 feet of 12-in., 650 feet of 16-in., and 400 feet of 12-in. pipe in sections. Use engineering judgment when analyzing the results.
Regards,
Jesse DringoliTechnical Support Manager, OpenFlowsBentley Communities Site AdministratorBentley Systems, Inc.