I am working on project where I have 7 segments that I have added into SS4, to clean up. The field crew is bringing in new segments. How do I add the new segments in without overwriting my changes in the previous segments? Doing very little editing in CAICE, so the Caice database and the SS4 data are different once I edit the segments in SS4.
Answer Verified By: paul gonzalez