<?xml-stylesheet type="text/xsl" href="https://communities.bentley.com/cfs-file/__key/system/syndication/rss.xsl" media="screen"?><rss version="2.0" xmlns:dc="http://purl.org/dc/elements/1.1/"><channel><title>Ac_1985's Communities Activities</title><link>https://communities.bentley.com/members/733a9be2_2d00_eab9_2d00_4fff_2d00_960c_2d00_4fdcb42d5139</link><description>Recent activity for people in Ac_1985's community</description><dc:language>en-US</dc:language><generator>Telligent Community 12</generator><item><title>Design Databases Heatlosses</title><link>https://communities.bentley.com/products/building/performance/f/hevacomp-forum/117555/design-databases-heatlosses</link><pubDate>Wed, 30 Mar 2016 10:44:22 GMT</pubDate><guid isPermaLink="false">6dad98f5-dbc9-4c4d-a9ba-e9da8dc6aa8e:6a1288f6-62dc-40ec-b75b-80bd57ebc163</guid><dc:creator>Ac_1985</dc:creator><description>&lt;p&gt;Hi,&lt;/p&gt;
&lt;p&gt;I am using design database for heatloss calculations for a student accommodation.&amp;nbsp; I am querying the results of the heatloss calculations as it returning results of between 30-40 w/m2, when we would expect to see a heatloss of around 60-70 w/m2.&lt;/p&gt;
&lt;p&gt;Below is the data that I am using.&lt;/p&gt;
&lt;p&gt;Wall Height 2.7m&lt;/p&gt;
&lt;p&gt;Partition Height 2.4m&lt;/p&gt;
&lt;p&gt;Ceiling Void 0.2 m&lt;/p&gt;
&lt;p&gt;Window 1m2&lt;/p&gt;
&lt;p&gt;Building set in Edinburgh with design temp of -5&lt;/p&gt;
&lt;p&gt;I am still awaiting U-values from the architect but as a default I have been using the maximum u-values for building elements from section 6.&lt;/p&gt;
&lt;p&gt;Wall 0.27 w/m2K&lt;/p&gt;
&lt;p&gt;Floor 0.22 w/m2k&lt;/p&gt;
&lt;p&gt;Roof 0.2 w/m2k&lt;/p&gt;
&lt;p&gt;Windows,doors, windows and roof lights 2.0 w/m2k.&lt;/p&gt;
&lt;p&gt;The floor area of a typical room is 15m2 and the building is 2 storeys high, with exposed floors and roofs set up.&amp;nbsp; Does 30-40 w/m2 appropriate using the values that I have used?&amp;nbsp; I can submit the model if required.&lt;/p&gt;
&lt;p&gt;Thanks in advance,&lt;/p&gt;
&lt;p&gt;&lt;/p&gt;
&lt;p&gt;Andrew&lt;/p&gt;
&lt;p&gt;&lt;/p&gt;
&lt;p&gt;&lt;/p&gt;&lt;div style="clear:both;"&gt;&lt;/div&gt;</description></item><item><title>Section 6 Scotland Update for SBEM</title><link>https://communities.bentley.com/products/building/performance/f/hevacomp-forum/111800/section-6-scotland-update-for-sbem</link><pubDate>Thu, 01 Oct 2015 10:13:08 GMT</pubDate><guid isPermaLink="false">6dad98f5-dbc9-4c4d-a9ba-e9da8dc6aa8e:84fd4ae5-6bdd-4ac4-8e63-d54bd18dcb6f</guid><dc:creator>Ac_1985</dc:creator><description>&lt;p&gt;Hi Guys,&lt;/p&gt;
&lt;p&gt;Any dates yet for when the New Section 6 Scotland update patch will be available for version 26?&lt;/p&gt;
&lt;p&gt;&lt;/p&gt;
&lt;p&gt;Thanks&lt;/p&gt;
&lt;p&gt;&lt;/p&gt;
&lt;p&gt;Andrew&lt;/p&gt;&lt;div style="clear:both;"&gt;&lt;/div&gt;</description></item><item><title>Netsys Hot Water Pipe Sizing</title><link>https://communities.bentley.com/products/building/performance/f/hevacomp-forum/102073/netsys-hot-water-pipe-sizing</link><pubDate>Thu, 23 Oct 2014 10:43:23 GMT</pubDate><guid isPermaLink="false">6dad98f5-dbc9-4c4d-a9ba-e9da8dc6aa8e:f82e7399-5b11-4ae8-8e66-8d8367d76c80</guid><dc:creator>Ac_1985</dc:creator><description>&lt;p&gt;Hi&lt;/p&gt;
&lt;p&gt;I am trying to size a hot water system on Netsys.&amp;nbsp; My brief requires me to have the return pipe work 2 sizes below the flow pipe size.&amp;nbsp; I use the fix pipe option to fix the return pipes accordingly.&lt;/p&gt;
&lt;p&gt;I have used floor change connectors to pass up through the floors.&amp;nbsp; The system is all connected fine, but the system will not allow me to&amp;nbsp;change the&amp;nbsp;size of the pipework between the ceiling&amp;nbsp;void height of the&amp;nbsp;first flow and the space between the second floor slab.&lt;/p&gt;
&lt;p&gt;My ceiling void height on the first floor is 2.6m high, the height of the 2nd floor FFL is 3.69m.&amp;nbsp; The pipe is set up to go from the ceiling void height then on special to 3.69m at this point a floor change connector is placed on top at 3.69m for the first floor and the height set for 0m on the 2nd floor level.&amp;nbsp; I then connect a special at 0m which then rises to the ceiling void height.&lt;/p&gt;
&lt;p&gt;&lt;a href="/cfs-file/__key/communityserver-discussions-components-files/275871/Capture.PNG"&gt;&lt;img src="/resized-image/__size/940x0/__key/communityserver-discussions-components-files/275871/Capture.PNG" alt=" " /&gt;&lt;/a&gt;&lt;/p&gt;
&lt;p&gt;Section 53 is coming up from the ground floor&lt;/p&gt;
&lt;p&gt;The size of the F &amp;amp; R are 160 and 108&lt;/p&gt;
&lt;p&gt;Section 64 is feeding the first floor coming from the riser.&lt;/p&gt;
&lt;p&gt;Section 65 F &amp;amp; R are 133 and 28 the return requires to be 76mm (This section rises from the first floor ceiling void height to the height of the 2nd floor slab).&lt;/p&gt;
&lt;p&gt;Section 76 Rises F &amp;amp; R are 133 and 76 this section rises from the second floor slab height of 0m to the second floor ceiling void height.&lt;/p&gt;
&lt;p&gt;Section 65 is the section I am unable to change.&lt;/p&gt;
&lt;p&gt;&amp;nbsp;&lt;/p&gt;
&lt;p&gt;&amp;nbsp;&lt;/p&gt;
&lt;p&gt;&amp;nbsp;&lt;/p&gt;&lt;div style="clear:both;"&gt;&lt;/div&gt;</description></item><item><title>DDB Hostel Rooms reverting to 24/7 Bedroom</title><link>https://communities.bentley.com/products/building/performance/f/hevacomp-forum/102007/ddb-hostel-rooms-reverting-to-24-7-bedroom</link><pubDate>Tue, 21 Oct 2014 09:31:04 GMT</pubDate><guid isPermaLink="false">6dad98f5-dbc9-4c4d-a9ba-e9da8dc6aa8e:f4bd7b36-8c24-449b-bfb1-f4ed02edbc72</guid><dc:creator>Ac_1985</dc:creator><description>&lt;p&gt;I am trying to set up a model for a care home.&amp;nbsp; When setting up the room type for a hostel/ nursing home the rooms are reverting to 24/7 Bedrooms.&amp;nbsp; I have tried to up date the file using the information from &lt;a href="/products/building/performance/w/building_performance__wiki/12119.hostel-room-types-reverting-to-24x7-bedroom-after-definition"&gt;http://communities.bentley.com/products/building/performance/w/building_performance__wiki/12119.hostel-room-types-reverting-to-24x7-bedroom-after-definition&lt;/a&gt;.&lt;/p&gt;
&lt;p&gt;When I copy over the unzipped file to the HEVADATA folder it comes up with an error and will not copy over.&lt;/p&gt;
&lt;p&gt;The Version of Hevacomp that my company are running is 25.06.9.&amp;nbsp; the version required for the update is 25.06.15.&amp;nbsp; My system administrator tells me that we have service pack 29 installed.&lt;/p&gt;
&lt;p&gt;Anybody any ideas for what I can do?&lt;/p&gt;