• RE: Schedule health check

    Hi Michiel, Brigt pointed me to your question and I think I can answer it. Critical Path Test is not the same as the ability to see the critical path in the schedule correctly. This test focuses on assessing the integrity of the logic in the schedule…
  • RE: Grouping gantt chart by activity code

    Hi Michiel, In Options -> Gantt Chart -> Activity Code mode you can choose to display the code value name and the code description: Best regards, Alex B
  • MS Project XML user field import issue

    I have a MS Project schedule with a user field which I have saved as a XML file in MS Project 2013. When I import the XML in to Synchro Pro 2019 6.1.1.1 the user fields do not import. The import window shows a zero count for user fields, how can I get…