You are currently reviewing an older revision of this page.
When closing, or updating, a work order the system is not presenting the In Progress (and potentially other) status.
Not all Work Order and Work Order Task Statuses are manually selectable, most are actually populated by the application's business logic. The "In Progress" status is one of those that cannot be selected manually. Bentley APM Asset Reliability / Ivara SuprEAM software selects "In Progress" when one or more Indicators have received readings or when activities (other than marking the work order as completed or closed) have been reported to the work order tasks.The following link will direct you to the section of our online help guide that explains the various statuses, when they assigned to a work order task and what activities are allowed to be performed against them.
http://help.ivara.com/7/en/eam/wwhelp/wwhimpl/js/html/wwhelp.htm#href=Work_order_statuses.html