Problem description

When user deletes Events from Events Tab of Request For Work on a Checksheet, the Work Priority and End Before date fields are not getting updated in General Tab.

Solution

The event is one of the ways the priority and date can be set. Priority can also be set based on asset defaults or simply manually entered. 

If the system is configured so an Event is mandatory, the User will be required to enter a replacement Event before the Request For Work can be completed. This will reset the priority based on the New Event.

The User can manually change the priority and date if appropriate.