Product(s): | APM Implementation and Performance Management | ||
Version(s): | 7 | ||
Environment: | N/A | ||
Area: | N/A | ||
Subarea: | N/A |
An APM user found that in some cases the Mobile Computing Activity's percent completion was not matching the related checksheet's percentage completion even after the activity has been marked as completed and processed.
The issue is that the Mobile Activity completion percentage is incorrect, note that it does not match the checksheet completion percentage. The checksheet completion percent is calculating correctly, whereas the Mobile Activity completion percentage is not calculating properly and is calculated independent of the checksheet completion percentage.
User should reference the checksheet's percentage completion when there is a question regarding completion.
This was reported as a bug, VSTS#984730.
SR 7001420800.