The default distance from first row of PS strands to bottom of I-beam is 2 inches in LEAP Bridge Concrete, how do I make it other than 2 inches, say 2.5", to compensate 1/2" beam end dapping? Thanks.
https://communities.bentley.com/products/bridge_design___engineering/w/bridge_design_and_engineering__wiki/47638/how-to-add-modify-height-and-or-of-strands-for-an-existing-beam-section-in-precast-prestressed-girder-module
Here are the steps to add or modify strand location for Precast/Prestressed Beam sections:
Answer Verified By: Dilip Matange [Bentley]
Thanks Dilip, appreciate your help.