Open Bridge Modeler to Leap Bridge Steel Overwriting Issue

Open Bridge Designer Version: 10.08.01.30

Open Bridge Modeler Version: 10.08.01.87

Leap Bridge Steel Version: 20.00.00.24

I am having difficulties with using leap bridge steel within the open bridge designer application. I am finding that each time I go into LBS from OBM (BIM workflow), various aspects of my design are overwritten and need to be re-entered (specifically sacrificial deck thickness, shear connectors, wearing surface information, & load combinations). I have not been able to figure out how to prevent this from happening, and it is not feasible to re-enter the information every time I go back into LBS. Is there a specific aspect of the workflow that I am misusing to cause this to happen?

Thank you,

Andrew Lemieux