I have a roadway project that is shoulder widening, bridge approach improvements, and bridge replacements. I have an alignment (from roadway design) where the existing ground profile is set as the active profile, for the shoulder widening. There are 3 bridge crossings that have profiles created in the roadway alignment file for the approach work and the bridge replacements; they are not set to active. The roadway models in the approach areas are modeled using the independent 'bridge' profiles as the basis of their roadway model.
My question...is there a way to model an OBM bridge using these independent profiles that are not set to active?
OBD 10.10.00.26OBM 10.10.00.786
Thanks,
Jamie