Hi!
I would like to copy my active profile a few meters horizontally. So, I offseted my element horrizontally from existing active one and projected profile to element.
And now I need to have only "new" projected profile to be active because I have to have new alignment for my bridge. But still my working point is in "old" profile.
Is it possible to change it or another way to fix it? I add I'm not interest to create new profile, I want to copy existing profile only.
Greetings, Andrzej
Select the new profile with the Element Selection tool. Then, move your mouse off the profile then hover over it. Several icons will appear and the second one will let you make the new profile the "active" profile.
Thank you Steve.
But if I do it, my new profile which I copied is also active.
I understand that is the same profile because I projected it. But I need to align my bridge to this new copied alignment which is moved a few meters horizontally. When I removed old one, both disappears.
After copying the profile, one of the icons there should allow you to break the civil rule at which point should be able to make the new profile active.
Thank you, it seems to work.