Document Type: FAQ Product(s): LEAP RCPIER/Substructure Version(s): All Original Author: Bentley Technical Support Group - VM
Document Type: FAQ
Product(s): LEAP RCPIER/Substructure
Version(s): All
Original Author: Bentley Technical Support Group - VM
ANSWER:
The program designs the drill shaft based on the values of H and h1 . h1 value is below the ground and H-h1 is the value between the bottom of the column and top of the ground.H-h1 value is used in the frame action to calculate the moment on drill shaft and anything below the ground is designed only for the gravity load. RC pier does not handle soil interaction for Drill shaft.