Loads definitions


The Loads definitions in RM Bridge inside OpenBridge Designer generally follow the workflow below:

  1. Select Schedule > Load Definition > Load Set to split the applied loads into logical sets of loads.
  2. Select Schedule > Load Definition > Load Case Definition to combine any number of load sets to compose the load cases, including the definition of load factors.
  3. Select Schedule > Load Definition > Load Management to establish the load management system. These are rules for combining the load cases during the stages of the schedule.

More detailed information can be found in each specific Wiki article, at the Online help F1 and at the sections of the User Guide document.