So what is the best way to get schedule of doors within space name , specially common door between two spaces ,because by using report from space planner you will get "various" for the common doors
ex :
Make sure that you don't have any doors with a frame in one wall and a swing through another as shown here:
I'm having the same problem. 1 door between to spaces and it "belongs" to both spaces. Is there something else to take into account when building the spaces or placing the doors to get only 1 space per door?
Ustn since 1988SS4 - i7-3.45Ghz-16 Gb-250/1Tb/1Tb-Win8.1-64bEric D. MilbergerArchitect + Master Planner + BIMSenior Master Planner NASA - Marshall Space Flight CenterThe Milberger Architectural Group, llc