Hopefully someone can clarify what I am missing in my setup of Floor Manager.
The two appended screenshots illustrate the issue.
When trying to select a floor in Floor Manager 'Set Active Floor' dropdown there is always a 'None' floor inserted below the 'Site' level in the dropdown hierarchy that prevents me from selecting a floor level below the "Building' level where it should rightfully be.
This 'None' floor is nowhere to be found in the Floor Manager setup toolbox.
Please help. I know I'm missing something.PDFPDF
Hi Rodney,
That "None" floor is a default, it can't be removed. You can, however, double click the floor that you want to work on and make it the active floor before you started placing your elements.
HTH.
Regards,
Satadal
Answer Verified By: Steve Cocchi
Many thanks Satadal,
Have not used Floor Manager for some time so needed a refresher.
All the best