Hi
When I'm trying to set up a new HWS system on the HWS tab system 1 is being copied to system 2 and vice versa. Anyone got any ideas ?
Haha! Not at all! All good stuff so we can keep improving the software for you guys :)
Shane Regan | Principle Building Performance Support Engineer
Thanks Shane - you must really hate me , glad I'm not going mad. Thaks for your help again.
Hi Graham,
I think I see what you mean here. The software seems to be expecting just one HWS to be added at a time - so you'll just need to make sure the changed data gets written before proceeding to the next one.
Basically all this means is you should edit one HWS only, and when done just exit the PartL window, reopen PartL, and then move onto the next HWS, and so on.
I will log this with development so the data gets written automatically.
Answer Verified By: Shane Regan
Hi Shane, I've shut down the program, restarted my pc, etc and still the problem persists
I am taking a look into this now for you, will be in touch shortly.