Hi,

I have carried out the SBEM calculation under Scotland Building Regulation 2022 Under PartL 2021. and i found there is a deviated result coming up in 'Results' Page and section 1 of Compliance Report. I extracted the relevant page for your information in which 123.61 kWh/m2 year and 110.96kWh/m2 year is shown on them respectively. i guess theses two value shall be identical and represent the delivered energy rate in notional building.

Thanks 

Parents
  • Hi Brian,

    Just following up on this one from a while back.

    All is working fine with this, the software is showing the correct results there.

    The figures you mention are separate results - 123.61 is the energy consumption by end use total, which refers to the below data:

    Separate to this is the result of 110.96, which refers to the Target Delivered Energy Rate (TDER). Hope that helps to clarify.

    Shane Regan | Principle Building Performance Support Engineer

        

Reply
  • Hi Brian,

    Just following up on this one from a while back.

    All is working fine with this, the software is showing the correct results there.

    The figures you mention are separate results - 123.61 is the energy consumption by end use total, which refers to the below data:

    Separate to this is the result of 110.96, which refers to the Target Delivered Energy Rate (TDER). Hope that helps to clarify.

    Shane Regan | Principle Building Performance Support Engineer

        