Hi,
I have several different zones for heating and ventilation. One of the zones is going to have mixed mode ventilation. We have Windcatchers that do adequate cooling and ventilation for 8 months of the year which means that the AHU's will not need to be used during that period. The remaining four months of the year we will need the plant and the windcatchers, combined, to provide adequate cooling and ventilation. Can anyone point me to a document or explain how I create a profile for the AHU Zone that will have the AHU’s off from September through to May and then have a profile that allows the plant to be running from 10am to 4pm for the remaining months, May, June, July and August?
Thanks
Steve Brown | Bentley Systems
Hello Matt,
Can you clarify which software you wish to do this in? Are you talking about Design Database - PartL or Dynamic Simulation?
RegardsSteve