Is it possible to run low level pipe work and then have it rise up to high level (ceiling Void)???. For context , the pipe work is serving the building at low level and when it entres the building it rises up to high level within the ceiling void. Is the a way to do this or do you have to draw the full pipe network at one constant level, IE low level or at high level?????
When I draw the pipe work at low level and then change it to ceiling level when it entres the building , the pipe work looks like it is at an angle or slopping up instead of having a nice 90 degree upward transiton from ll to hl.
Any help on this matter is greatly appreciated.
Kind Regards
Seamus Murphy
Hi Seamus,
Yes you can indeed - you just need to trace your LL pipe, change the default pipe height to HL, and then click on the same end point of the LL pipe, where you wish to place the riser.
The first half of this article details how to do this.
Shane Regan | Principle Building Performance Support EngineerHevacomp to OpenBuildings - A complete guide for every user | Bentley Communities
Hi Shane , thank you for your response. Thats great cheers for the help , I wasnt to sure if I was to go about it in the same way as adding in a floor connector.
Seamus
No problem at all Seamus, glad that helped.