Hi,
Ive set up a chilled water circuit and keep getting run time error 5 when i try to calc the system - Any help would be appreciated.
Hi Shane, ive deleted the risers and im still getting the same error even when just trying to calculate the ground floor. I have started a new project and I've simply used a system marker and one emitter to see if i can calculate just that and again im getting the run time error 5!!!
Thanks Adam,
Is this a recent installation of the software? Could you please reply with a screenshot showing the Hevacomp parts installed in your control Panel Programs and Features menu, as below:
Shane Regan | Principle Building Performance Support Engineer
Hi Shane,
See below:
I may of solved the problem it seems the operating temperatures on the system marker of 20/25 deg C flow return will not work, however i can get it to work if this is changed!!
Hi Adam,
Thanks for the update, glad to hear it is now working for you. Just one thing on your image above - is Hevacomp Update 10 not listed also? I ask as the software consists of 3 parts and all must be installed for it to work properly.
I've only got the 2 missing the update 10 for some reason