For the Task Selected I am trying to transfer the Actual finish date of the Task to its Resources with the Status of "Pour". Example for Task selected all the resource should have the status "Pour" with date of "12/16/19"
Hello Zahid -
I do not think SYNCHRO Script currently supports this if this is what you are trying to do with Script.
However it is likely possible if you create a Resource UF to transfer the task AF there then manipulate it in Excel then import the updates from Excel.
I hope this helps.