Sorting columns in simulation

Hi everyone,

I really need a help for simulation. I attached picture below you can see there are 4 columns resources and 1 activity. I assigned a "column profile" which is moving "bottom to top" growth simulation.

How can i simulate these columns with numbers which i showed in picture. I dont want to divide my activity to the the subactivites(columns1, cılumns2...).

Is there a way to simulate ? 

Parents
  • Hello- In this case you will have to build activities for this detailed simulation. Unless "Left to Right" growth simulation is acceptable which will allow the piles to be installed one by one, I believe you will have to create additional activities for this. Thank you!

  • Hello Chen, one of my customer wants to use this detailed simulation. He asked me to use one by one columnswith this simulation tecnique. He has used Asta4d. This simulation technique can be used in Asta 4d. So the customer dont want to divide activities. He wants same Asta 4d skills. Maybe i should write an idea to the forum. Thank you for reply.

  • Hi- please submit an idea using one of the buttons on the top of the web page. If you can provide more information and if your client is willing to, please ask him to provide some screenshots and recording with detailed description so we understand a little better how this is currently done elsewhere. And certainly appreciate your feedback. 

Reply
  • Hi- please submit an idea using one of the buttons on the top of the web page. If you can provide more information and if your client is willing to, please ask him to provide some screenshots and recording with detailed description so we understand a little better how this is currently done elsewhere. And certainly appreciate your feedback. 