Resource Status are not showing up in my Ipad

Hi

I am trying to get resource status to be selectable on my ipad, but no matter what I did, it does not show up.

So this were setup

Assigned worker with emails to every task.

Assigned resources to every task.

Did I miss out something?

Parents
  • Hi Edgar,

    Please make sure you follow the following steps to set up your project.

    1. Create Resource Groups from Resources

    Resource Groups aggregates 3D Resources as individual packages by responsibility. You can create Resource Groups by selecting desired resources > right-click > Resource Groups > Create Resource Groups from Selected.

                

    2. Set up Resource Statuses

    Resource Status defines detailed steps and milestones beyond construction activities.

    1. Go to Navigator > Resource Statuses to open the Resource Statuses panel.
    2. Define a Status Set by selecting the Default Category and right-click to Add (or press the Insert key). Name it as Concrete. Define a Status by selecting the Concrete Status Set and right-click to Add (or press the Insert key). Name it as Formed. The new Resource Status will be indented under the Status Set. Repeat to add a new Status Rebar and Placed.
    3. Change Resource Status colors.
    4. Assigning Status Set to Resources.

      3. Create Human Resources

      1. In the Resources panel, right-click > Add Human > Add your name as a Human Resource.
      2. Right-click on the Resource panel column title > Customize Columns > Add Email columns
      3. Enter your email address for Bentley IMS.

      4. Assign Resource Group Personnel

      By assigning personnel to Resource Groups, you can define responsibility for each resource group packages. You can select a Resource Group > Go to Resource Group Properties > General > Personnel > choose from the Human Resources you have just created.

      5. iModel Synchronization

      Transaction synchronization to iModel needs to be finished before the next step. The transaction status can be checked in Transactions > Transaction history.

      Thanks!

      Siqi

      Answer Verified By: Edgar Chan 

    Reply
    • Hi Edgar,

      Please make sure you follow the following steps to set up your project.

      1. Create Resource Groups from Resources

      Resource Groups aggregates 3D Resources as individual packages by responsibility. You can create Resource Groups by selecting desired resources > right-click > Resource Groups > Create Resource Groups from Selected.

                  

      2. Set up Resource Statuses

      Resource Status defines detailed steps and milestones beyond construction activities.

      1. Go to Navigator > Resource Statuses to open the Resource Statuses panel.
      2. Define a Status Set by selecting the Default Category and right-click to Add (or press the Insert key). Name it as Concrete. Define a Status by selecting the Concrete Status Set and right-click to Add (or press the Insert key). Name it as Formed. The new Resource Status will be indented under the Status Set. Repeat to add a new Status Rebar and Placed.
      3. Change Resource Status colors.
      4. Assigning Status Set to Resources.

        3. Create Human Resources

        1. In the Resources panel, right-click > Add Human > Add your name as a Human Resource.
        2. Right-click on the Resource panel column title > Customize Columns > Add Email columns
        3. Enter your email address for Bentley IMS.

        4. Assign Resource Group Personnel

        By assigning personnel to Resource Groups, you can define responsibility for each resource group packages. You can select a Resource Group > Go to Resource Group Properties > General > Personnel > choose from the Human Resources you have just created.

        5. iModel Synchronization

        Transaction synchronization to iModel needs to be finished before the next step. The transaction status can be checked in Transactions > Transaction history.

        Thanks!

        Siqi

        Answer Verified By: Edgar Chan 