I have imported a general schedule from P6, so, inside Synchro I have created child tasks for most of these general activities that came from primavera. After this I have defined task progress for these child activities on Synchro which are defining an specific progress for the parent task of course. The question, is there a way to "synchronize to" primavera and it will update the progress of its "parent tasks" without adding the child tasks I created inside synchro?