Note that Baseline Start & Finish Dates are already present in the start & finish columns in Synchro but they are overridden by Actual Start & Finish Dates as soon as the actual the Primavera P6 Schedule containing Actual dates is synced into the synchro file. Also note that , the BL Start & BL Finish columns have always remained empty
Hi Khushal,
If you already have the Baseline Start & Finish Dates in SYNCHRO, have you tried to create first a baseline out of these dates in SYNCHRO and then to sync the schedule with the P6 schedule containing the Actuals?
Like this you will retain the Baseline Start & Finish Dates under a baseline you create in SYNCHRO.
Best regards,
Alex B
Hi team,
Sorry, please ignore the previous post. I am going to reframe the query again- "The BL Start & BL Finish columns are empty in Synchro , hence the baseline start and baseline finish dates are not present. How can I import/sync the baseline start & finish dates in synchro from Primavera P6 schedule?"Thanks
We cannot bring into SYNCHRO the baselines from P6.
There is a workaround though and it can be found here:
https://communities.bentley.com/products/construction/w/construction__wiki/41568/how-do-i-import-baseline-data-from-primavera-p6