Hi team, Can you suggest me the best way to import/sync Baseline Start & Finish dates from a Primavera P6 file into Synchro. Thanks

Note that Baseline Start & Finish Dates are already present in the start & finish columns in Synchro but they are overridden by Actual Start & Finish Dates as soon as the actual the Primavera P6 Schedule containing Actual dates is synced into the synchro file. Also note that , the BL Start & BL Finish columns have always remained empty