Hai, I wanna ask, when I import the XML file into Synchro. there's a difference amount between the material cost (somehow Synchro split into something undefined). for example concrete $100 in P6 dan suddenly it's changed to $73.3m3 and $27m3 is defined as a new item. Can I get an explanation about this?
Thank you.
hi Agatha,
I want to test to import the XML file and check more details. It is possible to share the XML to us?
https://communities.bentley.com/p/secure_file_upload
This folder is a secure folder, only Bentley staff have access to your file.
Best regards,
Indrawan
Hi Mr. Indra,
I already sent the schedule, please check if it is an error or there's a wrong step while exporting it.
I checked your XML file.
I found that because the Effective Resource Cost not fully cover the Task Duration.
The Task start from 28 December but the effective cost date is from 1 January. Need to change the effective cost date to 28 December or before.
Is there any setting in P6 for this?
Indrawan Wijaya
Hi Agatha,
I just check in P6, found that effective date is come from P6.
You can change the data in P6, export the schedule to XML, and import it in SYNCHRO, will show 100.
Answer Verified By: Jacqueline Chen
Hi Mr. Indrawan.
I have Checked It and it's right. I'm not set the date for resources. Problem solved. Thank you so much for your support.
Best Regards,
Rully