P6 XML Import Fail

Hai, I wanna ask, when I import the XML file into Synchro. there's a difference amount between the material cost (somehow Synchro split into something undefined). for example concrete $100 in P6 dan suddenly it's changed to $73.3m3 and $27m3 is defined as a new item. Can I get an explanation about this?

Thank you.

Parents Reply
  • hi Agatha, 

    I checked your XML file. 

    I found that because the Effective Resource Cost not fully cover the Task Duration. 

      

    The Task start from 28 December but the effective cost date is from 1 January. Need to change the effective cost date to 28 December or before. 

    Is there any setting in P6 for this? 

    Best regards,

    Indrawan Wijaya