I have created a User Field for Tasks called VOLUME. I have assigned the volume value of the 3D object to this UF using the following script:
When I transfer values from the User Fields of 3D Objects to the User Field of the tasks, the values only appear in the tasks that have individual resources assigned, on the other hand, in the tasks that have Resource Groups assigned, the values do not appear. For example, in the task “ESCALERA 2 ANDÉN 1” that has a Resource Group assigned instead of individual resources:
How can I transfer these values from Resource Groups?
Thank you very much
hi Sergi,
Please try this Script,
It will do summary from Group.
TASK(SELECTED).ASSIGN_UF("Volumen",FLOAT,SUM(GROUP.RESOURCE.UFV_ZERO("Volumen")))
Best Regards,
Indrawan Wijaya
Yes!! It works!.
It is important to keep capital letters for the UF (in my case).
Thank you very much Indrawan.
Sergi Ferrater
Ups... Yes you are correct, it is case sensitive.
Good it works.
Best regards,
Indrawan