Hi,
I have imported into Synchro an MS Project programme, via a created XML file. I have a set calendar within MS Project that covers particularly Saturday as a work day. When I import the calendar, Synchro does not recognise Saturday's as work days. I have been into the Calendars section under the Navigation tab and I can see the particular calendar I want ot use, ie the 6 day week claendar I created in MS Project. The problem is that I can't assign it within Synchro.
I have tried making hte 6 day week calendar the default, and I also select tasks and within the Calendar section choose "assign to selected tasks". No good, it stubbornly remains at 5 days.
I would appreciate some thoughts.
Thanks,
Scottie
Hi Scottie,
Once you select the calendar and assign it to selected tasks, does it update the calendar in the General tab under Task properties? Also, please remember to click on Reschedule under Plan ribbon after making the calendar update.
Best,
Paolomee