Calendar non-working time not matching imported XML

Hi,

I have imported into Synchro an MS Project programme, via a created XML file. I have a set calendar within MS Project that covers particularly Saturday as a work day. When I import the calendar, Synchro does not recognise Saturday's as work days. I have been into the Calendars section under the Navigation tab and I can see the particular calendar I want ot use, ie the 6 day week claendar I created in MS Project. The problem is that I can't assign it within Synchro. 

I have tried making hte 6 day week calendar the default, and I also select tasks and within the Calendar section choose "assign to selected tasks". No good, it stubbornly remains at 5 days.

I would appreciate some thoughts.

Thanks,

Scottie