This discussion has been locked.
You can no longer post new replies to this discussion. If you have a question you can start a new discussion

Synchro 6.2.3.0 Isolating objects with too many tasks.

Hello, 

We have a project program with more than 6000 tasks, and while assigning objects to these tasks, we have made several errors assigning objects to too many tasks. 

We would like to ask, how do we go about isolating / filtering objects that have more than 2 tasks assigned to, or is there any other tool that could help to indicate these tasks.

Thank you 

Kind Regards

Martins