Hello,
We have a project program with more than 6000 tasks, and while assigning objects to these tasks, we have made several errors assigning objects to too many tasks.
We would like to ask, how do we go about isolating / filtering objects that have more than 2 tasks assigned to, or is there any other tool that could help to indicate these tasks.
Thank you
Kind Regards
Martins
Hi Martins,
You can either use the column Task IDs or create a User Field 'Task Count', and use them to filter/select the Tasks that these Resources have been assigned to multiple times.