I have one question about creating schedule operation.
The below is the example.
User A has the responsibility for Task A. Duration for Task A is 8 hours. And he is using 2 hours per 1 day for this task.
In this case, when assigning User A to Task A, it spends 4days.
For indicating the above, how should we define this on SYNCHRO?
The duration for Task A is automatically changed to 4 days?
If you need more information, please let me know.
Best Regards
Satoshi Matsuura
Satoshi,
You will be able to achieve that by editing the time block in the calendar to 2 hours. Does that help?
Best,
Paolomee