I have a building project where I want to demolish one building and then build another in its footprint
Is it possible to show the demolition the existing building in Synchro? What are the commands?
How do I set this up in 3D (I use Revit)
Do I do it in phases and then Synchro knows?
Thanks,
Aidan
Hi Aidan,
Are you using the SYNCHRO plugin or the iTwin Connector through SYNCHRO Control?
Hi Arpit
Revit 2021 and the SYNCHRO Pluggin
Thanks
SYNCHRO Plugin only exports what's visible in the current 3D View. To have better control over different phases of construction, you can create phase-specific 3D Views in Revit and export multiple SPXs from them. This will create a nice tree-hierarchy in 4D Pro.
Alternatively, simply expose all phases in Revit 3D View and export a singular SPX, but use User Fields to filter out Phase Construction in 4D Pro directly.
Answer Verified By: Aidan Hawkins
Thank you, and is this the same if I was exporting as IFC files and importing into Synchro 4d?
Yes, I believe the same applies to the IFC exporter for Revit.