The formula for calculating EAC(Estimate at Completion) for EVA is not listed in the help documentation.I would like to know which formula to use.
Hi HoSang,
I believe SYNCHRO uses standard EAC calculations, as explained in this article.
Planned Tasks, EAC = AC + Bottom-up ETC
Finished Tasks, EAC =BAC/Cumulative CPI
For Started Tasks, EAC = AC + (BAC - EV) or EAC = AC + [BAC - EV / (Cumulative CPI x Cumulative SPI)]
Answer Verified By: HoSang Jeon