Hi,
On SYNCHRO 4D Pro or SYNCHRO Cost, is it possible to register and manage the indirect cost?
(I have already known that it is possible to register and manage the direct cost such as human resource and materials.
Best Regards
Satoshi Matsuura
Hi Satoshi,
All Costs in SYNCHRO 4D Pro will have to come either from Resources or can be directly assigned to a Task -
You could technically use a Task to assign all of your indirect project-specific costs to it. However, keep in mind that you cannot assign Budgeted Direct Costs to Summary Tasks.