Hi,
The added tasks moved to the bottom of Gantt when the latest schedule is synced. Appears to be not in the correct parent tasks / sequence.
The new added tasks are highlighted in yellow in the attached image. Thank you.
Hi,Can you Check once Task id Repeated or Not in more than 1 task?if your given same task id in more than 1 task from your schedule data means may be creating this type of problem/ tasks. Thank you.Best Regards,Ashwin Rajesh K