4D Animation for Overlapping activities

Hello Everyone,

I have 2 Overlapping activities. Now I want to assign resources to the task and display the same properly in 4D simulation without changing the task date mentioned in the Baseline schedule. For example: (Please check the attached image.) I have Secant Piling activity which has 2 tasks- Drilling and Concreting for PCC piles and RCC piles. Now I want to show individual piling in 4D so for that I have assigned the resources using "Create new tasks under the main task" option. The issue is that now as the activities are overlapping the 4D visualization is not happening correctly. The RCC Piling should happen only if the PCC Piling for the nearby 2 piles is finished. Any suggestions to tackle this issue without changing the dates of activities would be helpful.