The Revit model was updated and I exported a new SPX file. How do I bring those changes in without losing the resource assignments?
1. Open the External Data window from the Navigator ribbon2. Find the originally imported SPX in the list3. Right click on the SPX name and select Synchronise From
4. Browse for the updated SPX5. Leave the Synchronisation settings as default:Existing/updated objects will remain assigned to tasks. Only new objects will need to be assigned.