Bentley Communities
Bentley Communities
  • Site
  • User
  • Site
  • Search
  • User
SYNCHRO Construction Solution
  • Product Communities
SYNCHRO Construction Solution
SYNCHRO 4D Wiki How can I filter by all activities under a WBS level?
    • Sign In
    • Features - SYNCHRO 4D Pro
    • Learning Resources
    • -SYNCHRO 4D Wiki
      • -SYNCHRO 4D Pro
        • +SYNCHRO 4D Pro - Best Practices
        • +Plugins and Tools
        • +SYNCHRO 4D Releases
        • -FAQ
          • SYNCHRO 4D Pro - System and Hardware Requirements
          • +General
          • +Import/Export/Synchronise Schedules
          • +Import/Export/Synchronize Models
          • +Scheduling
          • +Resources and Assignments
          • +3D Objects & 3D Paths
          • +3D View
          • -Filtering
            • How can I filter by all activities under a WBS level?
            • Show only 3D Objects assigned to Tasks
          • +User Fields
          • +Project Controls
          • +Animations & Reports
          • +Interoperability
          • Installing Synchro 4D using MSI and Silent Deploy Commands
          • Synchro 4D where can I install codecs from?
          • The user not able to see the Synchro 4D print dialog box due to window 11 operating system
          • Updating AMD Graphics Drivers
          • Updating Nvidia Graphic Drivers
        • +SYNCHRO 4D Pro - Troubleshooting
        • Unable to install Synchro 4D PRO
        • +SYNCHRO 4D Pro Guide (Work in Progress)
      • +SYNCHRO Modeler
      • +SYNCHRO 4D Schedule API
    • Upgrading from SYNCHRO Pro (and SWP) to 4D Pro (and Control)

     
     Questions about this article, topic, or product? Click here. 

    How can I filter by all activities under a WBS level?

    There is not yet a built-in task filter to do this, but it is on our list of improvements.

    One way to filter by WBS now is the following:

    1. Note that this method requires that WBS summaries have task IDs
      • If your schedule was imported from P6, they may not. To create IDs, go to Options>Synchronisation>Primavera P6 and enable Use WBS Code for Summary Tasks before Import or Synchronise From
      • To assign IDs in Synchro, select the WBS summaries with missing IDs and select Plan>Reassign IDs

    2. In the task list, right click in the header to Customise Columns
    3. Add the WBS Path column to the Selected Columns

    4. In the task list, right click in the WBS Path column header and choose Custom Filter
    5. Change the operation to Contains and enter the ID of the WBS summary for which you want to show all child tasks
    6. Optionally, Add another row to the filter and choose OR for the Logic to filter by a second WBS path
    7. The operation Matches can be used in filters in conjunction with wildcards (* or ? to replace any string or a specific character respectively)
    • Share
    • History
    • More
    • Cancel
    • Kate Hester Created by Kate Hester
    • When: Mon, Mar 18 2019 1:46 PM
    • Kate Hester Last revision by Kate Hester
    • When: Mon, Mar 18 2019 1:46 PM
    • Revisions: 3
    • Comments: 0
    Recommended
    Related
    Communities
    • Home
    • Getting Started
    • Community Central
    • Products
    • Support
    • Secure File Upload
    • Feedback
    Support and Services
    • Home
    • Product Support
    • Downloads
    • Subscription Services Portal
    Training and Learning
    • Home
    • About Bentley Institute
    • My Learning History
    • Reference Books
    Social Media
    •    LinkedIn
    •    Facebook
    •    Twitter
    •    YouTube
    •    RSS Feed
    •    Email

    © 2023 Bentley Systems, Incorporated  |  Contact Us  |  Privacy |  Terms of Use  |  Cookies