10.03.05.68 November 2022
10.03.03.56 December 2021
10.03.02.39 July 2021
10.03.01.48 April 2021
10.03.00.10 January 2021
10.02.00.43 August 2020
10.01.01.51 April 2020
10.01.00.23 January 2020
+
SYNCHRO 4D Schedule API
Upgrading from SYNCHRO Pro (and SWP) to 4D Pro (and Control)
You are currently reviewing an older revision of this page.
History
View current version
SYNCHRO AWP (formerly ConstructSIM) Modeling Known Issues
There is no upgrade path for user data
New product versions does not support data from previous versions and no upgrade path is possible.
Multi users conflict resolution is not supported
Cost code assignment and slicing operation conflicts are not handled and might result in incorrect data and geometry
No design change management
Cost code configuration updates are not supported
Volume is not calculated for some Earthworks and Fill elements
Performance decline: on bulk operations (above 1000) or when total assignments count above 5000
Instant crashes possible especially on decent machines with huge models and intensive usage
Calculated volume of sliced bridge barriers and deck components is different compared to the volume of the same components before the slice. Volume calculated before the slice is the correct one.
Sometimes volume value isn't calculated for one or two pieces of sliced component, when slice was performed on curved or bent component.
Sometimes application freezes when long road components are being split in two big parts. This doesn't happen when these road components are being split in smaller pieces.
Unit of measurement abbreviation in column "UOM" (in "Reporting" grid)
doesn’t change when calculated quantity is converted to another UOM using "Convert to" functionality. This issue is also seen in exported CSV file.
Order of assigned components is different in "Reporting" grid and exported CSV file:
in "Reporting" grid components aren't listed alphabetically
in exported CSV file
components are listed alphabetically
Order of assigned work steps is different as well:
in "Reporting" grid work steps are listed alphabetically
in exported CSV file work steps are listed according to work step code