After rescheduling, the task dates don't match those in my source schedule (P6, Asta, Microsoft Proj
Check your settings inNavigator>Project>Details:
Check theData Date- should usually be set toManualwith the last schedule update as the date
Check the setting forSchedule- should usually be set toASAP
Check theSchedule Fromoption - should usually be set toData Date
You may additionally check your settings inOptions>Gantt Chart>Rescheduling>Parameters. Select the Help button in the Options dialog to learn more about each of these settings.