SYNCHRO 4D Wiki When I export an animation, the focus time does not display ‘Week 1’ when the construction starts. Can I change the construction start week manually?
    • Sign In
    • Features - SYNCHRO 4D Pro
    • Learning Resources
    • -SYNCHRO 4D Wiki
      • -SYNCHRO 4D Pro
        • +SYNCHRO 4D Pro Guide
        • +Plugins and Tools
        • +SYNCHRO 4D Releases
        • -FAQ
          • SYNCHRO 4D Pro - System and Hardware Requirements
          • +General
          • +Import/Export/Synchronise Schedules
          • +Import/Export/Synchronize Models
          • -Scheduling
            • After recording Actual Finish Date for a Task A and Rescheduling, why does its successor Task B, with FS relationship, moves to the start of the Task A instead of starting after Task A finished date?
            • Can I display multiple ‘Project Week’ bars from different calendars on the Timescale in the Gantt?
            • Can I use SYNCHRO Scheduler to modify SYNCHRO Pro files?
            • How can I change the week number in the timeline so week 1 represents the beginning of the construction period?
            • How can I generate report for a time-distributed Resource utilization?
            • How can I get an S-Curve from SYNCHRO Pro to Excel?
            • How can I turn of link lines in the Gantt chart?
            • How do I create a 24/7 calendar?
            • How do we merge two separate SYNCHRO Pro SP files into one Master SP file?
            • Is it possible to expand the number of characters allowed in Activity Codes?
            • Is there a way to modify the Resource Appearance Profile for multiple Tasks?
            • Level Of Effort (LOE) vs Short Hammock vs Long Hammock
            • When I export an animation, the focus time does not display ‘Week 1’ when the construction starts. Can I change the construction start week manually?
            • Why can’t I navigate the Gantt Chart with a project with Tasks spanning upwards of 100yrs?
            • Why doesn't the Task progress finish line (blue fill) end at the Data Date line (vertical blue dotted line)?
          • +Resources and Assignments
          • +3D Objects & 3D Paths
          • +3D View
          • +Filtering
          • +User Fields
          • +Project Controls
          • +Animations & Reports
          • +Interoperability
          • Installing Synchro 4D using MSI and Silent Deploy Commands
          • Synchro 4D where can I install codecs from?
          • The user not able to see the Synchro 4D print dialog box due to window 11 operating system
          • Updating AMD Graphics Drivers
          • Updating Nvidia Graphic Drivers
        • +SYNCHRO 4D Pro - Troubleshooting
        • +SYNCHRO 4D Pro - Best Practices
        • Unable to install Synchro 4D PRO
      • +SYNCHRO Modeler
      • +SYNCHRO 4D Schedule API
    • Upgrading from SYNCHRO Pro (and SWP) to 4D Pro (and Control)

     
     Questions about this article, topic, or product? Click here. 

    When I export an animation, the focus time does not display ‘Week 1’ when the construction starts. Can I change the construction start week manually?

    SYNCHRO Pro displays the ‘Week 1’ at the Start of the project, regardless of first Task start date. This can be set under Navigator > Project Start.

    • Share
    • History
    • More
    • Cancel
    • Alex Buzan Created by Bentley Colleague Alex Buzan
    • When: Mon, Nov 30 2020 9:10 AM
    • Revisions: 1
    • Comments: 0
    Recommended
    Related
    Communities
    • Home
    • Getting Started
    • Community Central
    • Products
    • Support
    • Secure File Upload
    • Feedback
    Support and Services
    • Home
    • Product Support
    • Downloads
    • Subscription Services Portal
    Training and Learning
    • Home
    • About Bentley Institute
    • My Learning History
    • Reference Books
    Social Media
    •    LinkedIn
    •    Facebook
    •    Twitter
    •    YouTube
    •    RSS Feed
    •    Email

    © 2023 Bentley Systems, Incorporated  |  Contact Us  |  Privacy |  Terms of Use  |  Cookies