Bentley Communities
Bentley Communities
  • Site
  • User
  • Site
  • Search
  • User
SYNCHRO Construction Solution
  • Product Communities
SYNCHRO Construction Solution
SYNCHRO 4D Wiki Cost Code Setup
    • Sign In
    • -SYNCHRO 4D Wiki
      • +SYNCHRO 4D Pro
      • -SYNCHRO Modeler
        • +What's new
        • -SYNCHRO Modeler - Guide
          • SYNCHRO Modeler - Getting Started
          • iModel Index
          • +Default View
          • -Quantity Take-Off View
            • Slice
            • Cost Code Setup
            • Cost Code Assignments
            • Assignment Grid
            • Export Assignments to Excel
          • +Area Break Down View
          • Design change management
        • +SYNCHRO Modeler - FAQ
        • +SYNCHRO Modeler - Known Issues
      • +SYNCHRO 4D Schedule API

     
     Questions about this article, topic, or product? Click here. 

    Cost Code Setup

    This widget lists all the Cost Codes that are available across all the iModels in a Control project and can be assigned to selected 3D element(s).

     

    Cost Codes can be populated in SYNCHRO Modeler by uploading an Excel configuration file in a SYNCHRO Control project. Only users assigned with a Role having the following permissions will be able to view (Read iModel quantities) or edit (Administrative iModel quantities) the configuration -

    The configuration files can be downloaded from SYNCHRO Control > Administration > Cost Code configuration > Actions dropdown.

    Download sample file downloads an Excel configuration template that is prepopulated with sample data to help set up cost codes.

    Download template downloads an empty Excel configuration template.

    Configuration rules downloads a word document containing detailed information on how to work with various data and schemas to set up the configuration file.

    Formula rules downloads a word document containing detailed information on how to use formulas for Work step calculations.

     

    Cost Codes Configuration 

    Intro

    This sheet provides a brief overview of how to use different aspects of the configuration file.

    Variables

    Automatically calculated variables
    Currently, only the following automatically calculated variables are supported: $$area, $$volume and $$each. Quantities are calculated automatically for the Work steps where these variables are specified in the formula.

     

    Model Based Variables
    Any model/design measurement like length, height, weight, or element properties can be used as a model-based variable in the quantity formula. You can specify a measured value for these variables directly from the model in SYNCHRO Modeler as well.

     

    Project Variables
    These are used to describe project or company wide variables like asphalt density, waste factor, etc., that are not queriable from the model. It is important to take unit of measurement (UOM) into consideration when specifying values for the project variables. The variable name must have "$" as prefix.

    Geometric-extraction

    Geometric extraction defines which surface or surfaces,  or the whole object itself is used for calculations. Currently, only “Object / Element” geometric extractions are supported.

      

    Unit of Measurement (UOM)

    A list of all default UOMs with their abbreviations are provided and can be used in Work steps. Custom UOMs can be added considering the following rules -

    • All units used in Work steps formulas should be defined in UOM sheet
    • Specify ‘Custom’ classification in column A, leave Unit Name column empty and specify appropriate abbreviation in column C
    • All abbreviations should be unique
    • Two different “Unit Names” cannot have the same abbreviation
    • Do not modify, delete, or add new names for Length, Area and Volume units of measurement (column B) as it may result as a failure during configuration file upload
    • Abbreviations (column C) of Length, Area and Volume units of measurements can be changed



     
    Work steps

    This sheet lists all the Cost Codes, the Work steps with calculation formulas, that will be assigned to selected 3D model elements in SYNCHRO Modeler. Detailed instructions are provided in Configuration and Formula rule documents, but consider the following key pointers -

    • Each Cost Code should have at least one Work step
    • Multiple Work steps can be listed for the same Cost Code
    • Make sure to specify the Code and the Name for each line item
    • Information about parent Cost Code should be repeated in every row for all Work steps associated with it
    • All variables are correctly defined in their respective sheets

     

    Cost codes Level 1-7 defines the parent-child tree hierarchy for Cost Codes.

    Work steps defines the formula for extracting quantities from the model.

    Code requires a unique code that is assigned to the model

    Name is the name of the Work step

    Type can be a custom defined value that can be used for categorization

    UOM is the unit of measurement for the calculated quantity

    Geometric extraction specifies how the geometry is read for calculations. Currently, only “Object” is supported.

    Formula Calculation is used for calculating the model quantity

    Total/Roll-up aggregates the quantities to the specified Cost Code

    Volume UOM is the default unit of measurement to be used for volumetric calculations.
    Eg. UOM for a Work step is “lb” with formula “$$volume*$$$length” but will use “yd3” for the volume.

    Area UOM is the default unit of measurement to be used for area calculations.

      

    Cost Codes Upload

    Upload the Cost Code configuration through SYNCHRO Control > Administration > Cost Codes configuration.
       

    If there’s already an existing cost code configuration, click Replace to update it with a new configuration.

    Note: Even though existing configurations are preserved, there’s a chance that they might be incompatible and may be removed. 

    Note: There is no way of downloading an uploaded Cost Code configuration and must reach out to the original creator for a copy.

    Upon upload, the configuration file goes through a validation process, and displays a count of all entities like Cost Codes, Work items, a list of Project variables, and Top level Cost Codes.
      

    The validation also looks for any errors in the configuration file and provides information to fix them.

    Once the cost code is successfully uploaded, we will see the cost code in SYNCHRO Modeler like below.


    Video - 
    Play this video

    • Share
    • History
    • More
    • Cancel
    • Arpit Prakash Created by Bentley Colleague Arpit Prakash
    • When: Thu, Dec 22 2022 12:10 PM
    • Indrawan Wijaya Last revision by Bentley Colleague Indrawan Wijaya
    • When: Tue, Feb 21 2023 1:48 AM
    • Revisions: 6
    • Comments: 0
    Recommended
    Related
    Communities
    • Home
    • Getting Started
    • Community Central
    • Products
    • Support
    • Secure File Upload
    • Feedback
    Support and Services
    • Home
    • Product Support
    • Downloads
    • Subscription Services Portal
    Training and Learning
    • Home
    • About Bentley Institute
    • My Learning History
    • Reference Books
    Social Media
    •    LinkedIn
    •    Facebook
    •    Twitter
    •    YouTube
    •    RSS Feed
    •    Email

    © 2023 Bentley Systems, Incorporated  |  Contact Us  |  Privacy |  Terms of Use  |  Cookies