Baselines, Scenarios and Synchronization


Table of Contents

Baselines, Scenarios and Synchronization (Video)

Create Baseline and Synchronize Schedule

This section will introduce Create Baseline and Schedule Synchronization. Synchronization simply means to bring in updated information from updated models or schedule to 4D Plan/Model in Synchro. For schedule, there are Synchronize From and Synchronize To. For model files, there is Synchronize From in most cases. In the case of IFC, there is Synchronize To.

Create Baseline

Save a backup file and create a baseline in SYNCHRO:

You can find your saved baselines in Navigator ribbon > Baseline and Scenarios

Synchronize From updated schedule

Synchronization Options

If the task/3D object is imported from the old schedule / model into Synchro, but later it is deleted in updated schedule / model, it will be kept and will not be deleted in the 4D model in Synchro.

 

Note: Synchronization will work when the following is maintained in P6. 

Scheduling Tools (Video)

Model Based Scheduling (Video)

Practice Exercise – Piles (Video)


Challenge Model_Create high level Schedule (Video)

communities.bentley.com/.../Challenge-Model_5F00_Create-high-level-Schedule.sp

Challenge Model_Create high level Schedule_Solution (Video)

communities.bentley.com/.../Challenge-Model_5F00_Create-high-level-Schedule_5F00_Solution.sp