Hello,
We are looking to model an extraction well. I have input the minimum head and discharge rate in m3/day and had planned to run the analysis over an increasing number of days so that we could assess decrease in groundwater head in the area around the well against time spent extracting. However the results show the same groundwater head levels irrespective of number of days the stage is run over (I have tried between 1 and 30 days). Is there anything else I would need to input / conditions I need to change in the model to be able to calculate a time dependent head reduction?
Kind regards,
Maddie
Did you find a solution to this problem ?