Hi!
I work on a project in Plaxis 2D in which I make many charts to get the best solution.
In order to get the best solution, I make many recalculations and I always need the same charts.
How can the charts be updated after recalculation?
Or do I always have to generate the same charts as "new"?
Thank You in advance!
Dear Rebeka,
It is possible to update the charts based on the new results, provided that the generated mesh is not changed.
When viewing the chart, you can double-click on the legend or hit F3 or use the right-mouse button and select Settings. Then, you can choose the option to Regenerate the chart.
Thank you!