Updated mesh for Geogrids - active in all subsequent phases:

Hi 

Im undertaking an embankment design over soft soil, requiring piles and load transfer platform.

I have several geogrid layers and have activated them using the updated mesh option - they appear to be picking up tensile load, however the settlement remains very high between the columns such that there is a punching of the tip of piles through the load transfer platform. More design required, but i wonder if the updated mesh option is only required in a geogrid activation stage or must remain active throughout to capture 2nd order effects. I suspect the latter but looking to confirm.

Thanks

Scot

Parents Reply Children
No Data