GeoStudio | PLAXIS Wiki PLAXIS 2D Tutorial 06: Dry excavation using a tie back wall
    • Sign In
    • -Geotechnical Analysis Wiki
      • +GeoStudio
      • -PLAXIS
        • +Software and License - PLAXIS
        • -Documentation - PLAXIS
          • +Manuals - PLAXIS
          • -Tutorials - PLAXIS
            • -Tutorials PLAXIS 2D
              • PLAXIS 2D Tutorial 01: Settlement of a circular footing on sand
              • PLAXIS 2D Tutorial 02: Drained and undrained stability of an embankment
              • PLAXIS 2D Tutorial 03: Submerged construction of an excavation
              • PLAXIS 2D Tutorial 04: Settlements due to tunnel construction
              • PLAXIS 2D Tutorial 05: Excavation of an NATM tunnel
              • PLAXIS 2D Tutorial 06: Dry excavation using a tie back wall
              • PLAXIS 2D Tutorial 07: Dry excavation using a tie back wall - ULS
              • PLAXIS 2D Tutorial 08: Construction of a road embankment
              • PLAXIS 2D Tutorial 09: Excavation and dewatering
              • PLAXIS 2D Tutorial 10: Cyclic vertical capacity and stiffness of circular underwater footing
              • PLAXIS 2D Tutorial 11: Flow through an embankment
              • PLAXIS 2D Tutorial 12: Potato field moisture content
              • PLAXIS 2D Tutorial 13: Stability of dam under rapid drawdown
              • PLAXIS 2D Tutorial 14: Dynamic analysis of a generator on an elastic foundation
              • PLAXIS 2D Tutorial 15: Pile driving
              • PLAXIS 2D Tutorial 16: Free vibration and earthquake analysis of a building
              • PLAXIS 2D Tutorial 17: Thermal expansion of a navigable lock
              • PLAXIS 2D Tutorial 18: Freeze pipes in tunnel construction
            • +Tutorials PLAXIS 3D
            • Slope stability for road construction project: using FEM and LEM [PLAXIS LE]
            • Slope stability for road construction project: using FEM and LEM [PLAXIS and GeoStudio]
          • +Verifications - PLAXIS
        • +API / Python scripting - PLAXIS
        • +Known issues - PLAXIS
        • +Models - PLAXIS
        • +Tips and Tricks
        • +Publications
        • +Videos - PLAXIS
      • +PLAXIS Monopile Designer
      • +PLAXIS LE
      • +SOILVISION
      • +Geotechnical SELECT Entitlements [GSE]
      • +Subscription Entitlement Service

     
     Questions about this article, topic, or product? Click here. 

    PLAXIS 2D Tutorial 06: Dry excavation using a tie back wall

    Application PLAXIS 2D
    Version PLAXIS 2D
    Date created 20 May 2017
    Date modified 12 October 2022

    This example involves the dry construction of an excavation. The excavation is supported by concrete diaphragm walls. The walls are tied back by prestressed ground anchors.
    PLAXIS allows for a detailed modelling of this type of problem. It is demonstrated in this example how ground anchors are modelled and how prestressing is applied to the anchors. Moreover, the dry excavation involves a groundwater flow calculation to generate the new water pressure distribution. This aspect of the analysis is explained in detail.

    This exercise requires a PLAXIS 2D Advanced or PLAXIS 2D Ultimate license.

    The attached *.p2dxlog file contains all the commands to generate the model. With a Bentley Geotechnical SELECT Entitlement [GSE] licence, you can use the commands runner to open the *.p2dxlog file and to execute all commands in one go, see also this instruction.

    Downloads

    • Green book PLAXIS 2D CE V22.02 - Tutorial 06.pdf - instructions
    • Notepad spiral PLAXIS 2D CE V22.02 - Tutorial 06.p2dxlog [command log file]
    • Green book PLAXIS 2D CE V22.01 - Tutorial 06.pdf - instructions
    • Notepad spiral PLAXIS 2D CE V22.01 - Tutorial 06.p2dxlog [command log file]
    • Green book PLAXIS 2D CE V22 - Tutorial 06.pdf - instructions
    • Notepad spiral PLAXIS 2D CE V22 - Tutorial 06.p2dxlog [command log file]
    • Green book PLAXIS 2D CE V21 - Tutorial 06.pdf - instructions
    • Notepad spiral PLAXIS 2D CE V21 - Tutorial 06.p2dxlog [command log file]
    • PLAXIS 2D 2018 - Tutorial Lesson 03.pdf
    • PLAXIS 2D 2018 - Tutorial Lesson 03.p2dxlog [command log file]

    See also

    PLAXIS 2D Tutorial 05: Excavation of an NATM tunnel    [Tutorials]


    PLAXIS 2D Tutorial 07: Dry excavation using a tie back wall - ULS    [Tutorials]


    PLAXIS 2D Tutorial 08: Construction of a road embankment    [Tutorials]


    PLAXIS 2D Tutorial 09: Excavation and dewatering    [Tutorials]

    • Tutorial
    • Groundwater
    • prestress
    • embedded pile row
    • prestressed ground anchors
    • PLAXIS
    • PLAXIS 2D
    • excavation
    • Groundwater flow
    • diaphragm wall
    • Share
    • History
    • More
    • Cancel
    • Micha van der Sloot Created by Bentley Colleague Micha van der Sloot
    • When: Wed, Dec 18 2019 10:43 AM
    • Felipe Fonseca Last revision by Bentley Colleague Felipe Fonseca
    • When: Wed, Oct 12 2022 3:58 PM
    • Revisions: 8
    • Comments: 0
    Recommended
    Related
    Communities
    • Home
    • Getting Started
    • Community Central
    • Products
    • Support
    • Secure File Upload
    • Feedback
    Support and Services
    • Home
    • Product Support
    • Downloads
    • Subscription Services Portal
    Training and Learning
    • Home
    • About Bentley Institute
    • My Learning History
    • Reference Books
    Social Media
    •    LinkedIn
    •    Facebook
    •    Twitter
    •    YouTube
    •    RSS Feed
    •    Email

    © 2023 Bentley Systems, Incorporated  |  Contact Us  |  Privacy |  Terms of Use  |  Cookies