DIVERSION MODELING

Hi

how can I model the diversion in following captured?

Parents Reply Children
  • Hamid,

    Have you tried using the channel element and then connecting it with a cross section to your other channel element that is going to your treatment plants? What I envisioned your model looking like based on your first screen capture is something like this:

    Just make sure to connect the channel at about 20 meters from the manhole. You can do this by making the channel to the left of the manhole and the right of the cross section that connects to the diversion channel a user defined length of 20 meters.

    Also based on what you stated about your weir control structure not receiving flow until the flow in the weir is 100 gpm you might want to consider using depth-flow control structure type instead of the side weir. The depth flow control structure type will allow you to enter a table of depth vs. flow in the diversion channel.

    Regards,

    Mark 

    Mark

    Answer Verified By: Hamid.AKbari