Force main with SewerGems using SWMM engine

Hi,

In my sewerGems model I have a pump station with a force main of 2km and 1050 mm diameter. This force main is discharging in a chamber that is also the start of an inverted siphon (to cross a river).  I am using swmm engine. In the scenario summary, there is a small continuity and routing error (±1%) but there is a high percentage of non-converging (40%). I'm trying to find the reason of this non-converging high percentage. Here are my questions:

  1. I tried to model the force main as a pressure pipe with 6 pressure junctions (because there is slope change in the pipe) and one small virtual pipe between the pump and the first pressure junction. Is it the best way do to it?
  2. For the inverted siphon I used a tank on one side of the river and a transition node for the lowest point and the discharge is a manhole. I use gravity pipe. The results seem ok, but is it the best way to represent an inverted siphon?

Thank you