Hi,

I'm using Scada element in Sewergems to compare my results with field data. Unfurtunately when I graph all my Scada element only 24h is shown but the calculation options are set to 48h. I'm using SWMM solver and end date\ end time for duration type . I looked at the data in the graphs and there is 48h data (see below).

Do you know why ?

Thank you

Marie-Joelle

Parents Reply
  • Hello Marie-Joelle,

    You are likely using the 64-bit version of SewerGEMS still (the 32-bit and 64-bit installation files on the software fulfillment page on Bentley's website include both the 32-bit and 64-bit versions).

    Try browsing to C:\Program Files (x86)\Bentley\SewerGEMS and open SewerGEMS.exe. This is the 32-bit version of SewerGEMS. See if the issue still occurs. This link has more information on this. 

    Regards,

    Scott